Background
Blockbuster locations doubling for anywhere in the world are driving huge demand in Australia, coupled with the country's flattened COVID-19 curve. The international spotlight is firmly on Australia and this has seen the film industry experience a threefold increase on 2019 levels.
Case Summary
Movies are getting bigger and bigger, yet many don't realise that the industry owes a lot of its recent disruption to high-performance computing. Behind all the special effects and set designs of a blockbuster is the demand for compute-intensive applications and latency-free computing power.
Location: Australia
Vertiv Solution: Liebert APM, Liebert CRV
Results
Managed on schedule within just three weeks, the data centre not only met the specific noise requirements, but delivered a total cooling capacity of 24.4 kilowatts, keeping output at 19 degrees Celsius. Additionally, the Vertiv™ Liebert® APM UPS helped deliver a 94 per cent efficiency in double conversion.